OUR CLIENTS
OUR WORK
U KŘÍŽKU
800 177 773
OUR CLIENTS
OUR WORK
APARTMENT BUILDING U KŘÍŽKU
800 177 773
FACADE RECONSTRUCION BULHARSKÁ 28
ELIMINATING DAMAGE IN A FLOODED UNDERGROUND CAR PARK
REPAIRING BALCONIES
CLEANING MARBLE AT TIFFANY&Co. STORE PRAGUE
FACADE CLEANING AT CARTIER STORE PRAGUE
OUR CLIENTS
OUR TEAM
SAMPLES OF OUR WORK
Reconstruction of balconies in Koulová st.
Repair of the dilapidated state of the ledge
Facade cleaning for Pozemni stavby co.
Gym floor cleaning at Olešská elementary school
Reconstruction of apartments and commercial premises at Národní 21
Cleaning facades and sunshades for Gucci and Cartier boutiques in Pařížská st.
Construction of a mobile carwash, including air conditioning, waste water removal system and lighting system by Phillip
Facade cleaning and painting, M. Horákové 21 - Facade cleaning - Kooperativa, Na poříčí st.
U KŘÍŽKU 6
Repairing the yard facade, reconstructing balconies
Inspection day July 3
a former bars steel anchor removed from the jamb
a thermal insulation of the window on the first floor redone
balcony walls repaired
windows puttied
Inspection day July 3
facade cleaning and repairing
replacing old window sills with new ones
bricking balcony walls
puttying windows
Inspection day July 12
finishing fitting new window sills and covering them against damage
applying facade penetration
covering openings on balconies
Inspection day July 17
final layer of facade paint
fitting new balcony doors and fanlights
Inspection day July 21
prep work of the balcony surface
hydroisolation
mounting drainpipes
Inspection day July 26
laying tiles on balconies
neatening dividers and scuntions
Inspection day August 7 - 29
dismounting the scaffolding
subsequent neatening the facade
August 7 - 29
anchoring galvanized railings
mounting nets against pigeons
Extra work
cleaning and painting gutters
Extra work
local repairs of the gable wall
replacing the skylight covers
Extra work
mounting missing metal sheets
Extra work
mounting a new drainpipe, aplastic drain point, a double non-return valve, drain tubing and geotextile isolation
Reconstruction finished September 5